3.png

Standardization Works

FOR CODE F STANDS AT TERMINAL 1 OF HONG KONG INTERNATIONAL AIRPORT

CSI was the main contractor and executed the standardization works of Pre-Conditioned Air (PCA) systems and Fixed Ground Power (FGP) systems for Code F aircraft at parking stands.    

PROJECT DETAILS

  • Dismantled and relocated 5 sets of existing PCA system

  • Designed, supplied and installed 9 new sets of PCA systems including 75 TR ground-mounted & 120 TR bridge-mounted PCA systems

  • Dismantled and relocated 3 sets of existing FGP systems

  • Designed, supplied and installed 6 new sets of 90 kVA FGP systems plus 4x transformers

  • Modified the existing electrical system to suit the new PCA and FGP systems

  • Conducted operations and maintenance training

  • Testing and commissioning after installation

 
 
 
 

Project Completion Date: December 2017
Project Partner: Hitzinger GmbH

PARTNERSHIP DETAILS

  • CSI is the authorized agent of Hitzinger products in Hong Kong and China

  • Hitzinger FGP system was installed in this contract

  • We provided "One Stop Services" for this project

  • The site installation and testing was also carried out by the CSI team

  • The project was completed on schedule and the result met with the client's expectations

  • The CSI team also continues providing comprehensive after-sales services which is highly appreciated by clients