RTG R89 Semi-Automatic ROS

PILOT PROJECT AT MODERN TERMINAL LTD. (MTL)

CSI was awarded a contract from Siemens (SFAE) for electrical and mechanical installation of RTG semi-automatic remote operation pilot project at MTL Hong Kong.  

Siemens provided the electrical cabinet and components.

CSI was responsible for the replacement of the RTG master electrical system at E-Room and installation of corresponding electrical system, installation of the additional electrical equipment in the terminal yard, design, fabrication and installation of mounting brackets for equipment transformation, management of construction site and on-site commissioning assistance.

This was a challenging pilot project, lot of site surveys and repetitive trials were involved prior to final installation, Siemens and MTL were satisfied with the result at the end.

Project Completion Date: March 2018