HOME > EXPERIENCE > ECS Control System Electrical Installation Works in ADM Station – MTRC 965C
Job Name
ECS Control System Electrical Installation Works in ADM Station – MTRC 965C
Completion date
11/2015 - 12/2016
Job Details
CSI is responsible for MVAC Electrical installation from MCC and PLC control Panels to end devices such as motors and sensors etc., testing and commissioning.
 
The PLC IO counts

 

DI

DO

AI

AO

Total

2,304

1,696

200

44

4,244

 

In addition, CSI also involved all the control panels design, fabrication and on-site installation as complete solution package.
 
The project was completed on schedule and the result fully meets with client's satisfaction.